On 26 March 2026, SP Electricity North West (SP ENW) held its annual Distribution System Operation (DSO) Conference, bringing together the National Energy System Operator (NESO), Great British Energy, the Greater Manchester Combined Authority, and a wide range of industry stakeholders to discuss the future of electricity distribution across the North West.
For developers, contractors, and operators working in the region, the conference contained a significant amount of material that is directly relevant to how projects are planned, connected, and managed. We attended and have pulled together the key takeaways below.
1. The demand growth projections are substantial — and they are now the regulatory baseline
The transitional Regional Energy Strategic Plan (tRESP), published by NESO in January 2026, is the document that will underpin SP ENW’s next regulatory business plan. It sets out the demand the North West distribution network must be designed to accommodate, and the figures are significant.
Annual electricity demand across the region is projected to more than double by 2040, rising from 21 TWh today to 44 TWh. The technology driving that growth includes 2.5 million electric vehicles and 830,000 domestic heat pumps by 2040, growing further to 4.5 million EVs and 2.6 million heat pumps by 2050. Battery storage capacity is expected to reach 4.1 GW by 2040 and 7.4 GW by 2050.
These are not targets or aspirations. They are the Consistent Planning Assumptions (CPAs) that SP ENW is now required to use when building its investment case for Ofgem. For anyone working on projects that connect to the SP ENW network, this is the planning context that DNO investment decisions are being made against.
2. Seventeen areas have been formally designated for proactive network investment
One of the most practically useful outputs of tRESP is the Strategic Energy Need (SEN) mapping. Across the SP ENW licence area, 17 Grid Supply Point (GSP) areas have been identified as requiring proactive investment in network capacity — the highest number of any DNO area in England.
The top five by required capacity are:
- Capenhurst — 1.09 GW (industrial decarbonisation)
- Kearsley 123kV — 0.57 GW (commercial development and housing)
- Penwortham West Stanah — 0.57 GW (social infrastructure, data centres, commercial development)
- Harker Hutton — 0.28 GW (industrial decarbonisation)
- Carrington Fiddlers Ferry — 0.12 GW (industrial decarbonisation and housing)
Across all 17 areas, 3.4 GW of additional network capacity is required by 2034. For schemes in or near these zones, the DNO is already planning investment ahead of confirmed demand. Understanding where these areas are — and what is driving the need — is relevant to feasibility assessments, connection strategies, and programme planning on both residential and commercial projects.
3. The RIIO-ED3 business planning process is underway now
SP ENW is currently building its RIIO-ED3 business plan, which will cover the 2028 to 2033 regulatory period. This plan will determine the level of network investment Ofgem approves for that period, and it is being built on the tRESP framework — using the pathways, CPAs, and SEN designations described above as its foundation.
The plan is expected to involve around 120 Engineering Justification Papers and will be submitted to Ofgem ahead of the regulatory period. NESO will play an assurance role in reviewing parts of the submission. Draft business plan guidance from Ofgem is expected later in 2026.
For the industry, this matters because the investment decisions being made now will shape the available capacity and connection options in the North West for the next decade. Projects and schemes that can be connected to the SEN data validation process — which SP ENW is currently running with stakeholders — have an opportunity to influence where investment is prioritised.
4. Active Network Management is delivering faster connections and reducing the need for reinforcement
SP ENW’s Active Network Management (ANM) system enables flexible connections into constrained parts of the network by automatically monitoring and managing power flows in real time. In 2025/26, SP ENW dispatched 8,736 MWh of flexibility through the system — more than double the previous year.
The results from the first ANM connection in the licence area were notable: a customer’s connection date was accelerated by up to five years, and a 50% restriction on their import capacity that would otherwise have applied for most of the operating day was removed. More broadly, SP ENW reported accelerating generation connections by an average of six years and demand connections by four years through flexible connection arrangements.
For projects in capacity-constrained areas, ANM-based flexible connections are a genuine route to earlier energisation. However, they carry specific technical requirements around protection, metering, and communications infrastructure that need to be factored in at the design stage rather than discovered at commissioning.
The 2026/27 flexibility tender is now open. Commercial qualification can be completed at any time, with contracts awarded in October. Both long-term and monthly tender options are available.
5. Greater Manchester’s development pipeline is substantial and is being planned alongside network capacity
The Greater Manchester Combined Authority (GMCA) presented an integrated pipeline of growth locations spanning all ten boroughs. Headline schemes include 12,600 new homes at NorthFold in Bolton, 28,000 homes in the North East Growth Corridor, and 90,000 new jobs in the Central Growth Cluster across Manchester and Salford. The GMCA Good Growth Fund — a £1 billion blended investment fund launched in November 2025 and expanded in March 2026 — is backing priority schemes across the region.
What is notable from a network planning perspective is that SP ENW and GMCA are actively coordinating on this pipeline. They meet bi-weekly to discuss strategic development priorities, connection issues, heat networks, and Local Area Energy Planning. SP ENW’s Distribution Future Electricity Scenarios (DFES) forecasting model already incorporates Greater Manchester’s planned growth zones, meaning the network investment case for many of these areas is being built around the development pipeline rather than waiting for it.
For developers and their advisors working in Greater Manchester, this coordination makes early engagement with network data more productive. SP ENW’s substation capacity pages, DFES tool, and capacity heatmaps reflect a network planning picture that is informed by the GMCA’s growth ambitions.
6. Great British Energy is moving into active delivery
Great British Energy (GBE) received Royal Assent in May 2025. It is operationally independent from the Department for Energy Security and Net Zero and is backed by £8.3 billion of revenue across GBE and GBE Nuclear. Its mandate covers the delivery of over 15 GW of energy generation and storage capacity and the leveraging of £15 billion in private finance.
Its Local Power Plan, published in February 2026, targets support for more than 1,000 local and community energy projects by 2030, underpinned by up to £1 billion of investment. GBE’s onshore energy programme is focused on unlocking the generation potential of public land and investing in grid flexibility and storage. Its Local programme is developing scalable funding and business models for community energy organisations.
GBE’s transition from set-up to active project delivery represents a growing pipeline of publicly backed schemes across onshore renewables, community energy, battery storage, and grid-connected generation — all of which will require utility connections, network installation work, and ongoing asset management.
7. SP ENW’s open data is more useful than many in the industry realise
One of the more practically useful sessions at the conference was SP ENW’s presentation on their data and analytics offering. Their open data portal now holds 181 datasets, 94 of which are fully open and freely accessible.
For those working on projects in the SP ENW area, the most relevant tools include:
- The DFES visualisation tool — scenario-based demand and generation forecasts to 2050 at substation and local authority level
- Network capacity heatmaps and substation boundary flow information
- GSP connection queue data
- LV visibility data at half-hourly granularity
- The Low Carbon Technology Readiness Checker — property-level assessment of network readiness for EVs and heat pumps
SP ENW is also developing a shared licence data tier for more sensitive datasets, allowing authorised parties to access more granular information where there is a legitimate planning or development need.
These tools are available now and are directly useful in connection feasibility assessments, capacity planning, and grid-connected installation design. If you are not already using them, it is worth building them into your early-stage project process.
What this means in practice
The overall picture from the SP ENW DSO Conference is one of a network under significant and well-documented pressure, with a clear regulatory and investment framework taking shape around it. The tRESP process has created more transparency about where investment is coming and why. The RIIO-ED3 business plan will translate that into funded capacity upgrades. ANM is already helping projects connect faster in constrained areas. And the data to inform early-stage decision-making on all of this is largely in the public domain.
For developers, the implication is that early engagement with network data and connection strategy — rather than treating the grid as something to deal with once planning is secured — leads to better outcomes. For contractors and installers, understanding the technical requirements of flexible and ANM connections is increasingly a basic competency for working in constrained network areas. For asset owners and operators, the DFES forecasts and LV visibility data provide a clearer picture of how the network around your assets is expected to evolve.
The UIG group — through Utility Connections, Fusion Utility Networks, and Integrated Power Engineering — works across all of these stages. If you have questions about how these developments affect a specific project or scheme, we are happy to discuss.
Get in touch
Utility Infrastructure Group delivers concept-to-completion utility infrastructure services across feasibility, installation, and asset management. Our subsidiaries Utility Connections, Fusion Utility Networks, and Integrated Power Engineering work with developers, contractors, and network operators across the UK.